Projects co-financed from the state budget or state earmarked funds
"Changing the Architecture Model of the Logistics Network of Poczta Polska"
The project is co-financed by the Reprivatization Fund.
Funding: PLN 190,000,000
Total project value: PLN 357,205,688
Implementation period: 2021-2024
Project description
The Logistics Network Architecture (ASL) is one of the most important strategic initiatives of Poczta Polska, enabling the smooth transformation of the current logistics network, adapted mainly to handling letters, to a target network aimed at handling the increasing volume of CEP (courier, express and parcel) and e-commerce shipments.
The implementation of the ASL project aims to modernize Poczta Polska's current logistics network. This will enable the company to achieve its logistics goals, which are one of the pillars of its strategy, in the coming years, and further develop its business in the areas of CEP, e-commerce, logistics, and international services. The project also aims to improve the efficiency (increasing timeliness, network throughput, and optimizing costs related to shipment handling) of the current logistics network.
As part of the ASL project, Poczta Polska will gradually transform its logistics infrastructure from letter to parcel, responding to changes observed in the postal market both in Poland and globally. The capital injection will enable the modernization and construction of logistics centers that will provide modern services for the growing e-commerce market.
Project status
Start of adaptation works at the Dispatch and Distribution Hub in Lublin
As part of the preparations of the Dispatch and Distribution Hub in Lublin for the installation of a new sorter, Poczta Polska signed an agreement with the contractor on April 21, 2022, and with the substitute investor on April 13, 2022, who will carry out the construction works enabling the installation of the machine.
As a result of the tender process, the construction contractor FHU COMPLEX Marta Konieczna from Stary Sącz was selected, as well as the substitute investor ZDI Sp. z o. o. from Zamość.
Completion of adaptation works at the Dispatch and Distribution Hub in Lublin
The scope of work included changing the layout and functionality of the building, without affecting its shape or surface area. The construction acceptance and signing of the final report on the completed works took place on October 28th.
Machinery at the Dispatch and Distribution Hub in Lublin
The process of installing the sorter for automatic parcel sorting has begun. The device's support structure has been installed, assembly of the sorter's main line has begun, the vertical chute structures have been installed, and the manual feed zone has begun.
Launch of the sorter at the Dispatch and Distribution Hub in Lublin
The sorter for automatic processing of CEP shipments was launched on schedule. Installation of the sorter was performed by BEUMER Group Poland sp. z o. o. The cross-belt machine, with a total sorting loop length of 285 meters, has an operating capacity of 7,000 shipments per hour.
Start of adaptation works at the Dispatch and Distribution Hub in Wrocław
The mechanical upgrade of the Shipping and Distribution Hub in Wrocław is one of the key tasks within Poczta Polska's strategic project – Logistics Network Architecture. An integral part of this project is preparing the facility with the infrastructure necessary to accommodate the new sorter with the specified technical parameters.
On April 25, 2022, an agreement was signed with the contractor for adaptation works, Mostostal Warszawa SA.
The scope of adaptation works will include work inside the existing building and the addition of two facilities with a total area of 1,500 m2. Access roads with maneuvering areas at the new docks will also be modernized.
Completion of the first stage of adaptation works at the Dispatch and Distribution Hub in Wrocław
In accordance with the adopted schedule, the first stage of adaptation works at the Dispatch and Distribution Hub in Wrocław was completed on December 30, 2022.
The completed stage included the implementation of the investment as part of the expansion of the current facility with a newly constructed office building and a warehouse with a total area of over 1,500 m2, as well as the modernization of access roads with maneuvering areas at the new docks.
At the same time, advanced work is underway at the WER Wrocław facility, related to the installation of the sorter and further adaptation of the existing facility to the needs of installing the machine.
Completion of adaptation works at the Dispatch and Distribution Hub in Wrocław
Adaptation work at the logistics facility in Wrocław has been completed according to the approved schedule. This phase involved adapting the existing building to accommodate the needs of the automated parcel sorting machine being installed. Work is currently underway on the installation of the "Cross-belt" sorter by Beumer, and acceptance testing and IT system integration have begun.
Machinery at the Expeditionary and Distribution Center in Wrocław
Activities at the Wrocław sorting plant are being carried out on a large scale and at many levels. In addition to the adaptation work, additional office and warehouse space is being added. These works are being carried out both inside and outside the terminal hall. The goal is to free up space for the sorter and reconfigure the hall for future processes.
The installation of the sorter for automatic distribution of KEP shipments at the Wrocław sorting plant is handled by BEUMER Group Poland sp. z o. o.
The sorter installation is progressing according to schedule. After installing the sorter's support structure and the main line and chutes, the next steps are electrical and IT work. The sorter is scheduled to be operational in May 2023.
Launch of the sorter at the Dispatch and Distribution Hub in Wrocław
According to the adopted schedule, a sorter for automatic processing of CEP shipments was launched. The installed sorter will automatically read not only standardized address labels but also international shipments, which often have non-standard address data. The sorter was installed by BEUMER Group Poland sp. z o. o. The "Cross Belt" machine is equipped with four manual feeders, four automatic feed lines, 128 directional chutes, 56 vertical chutes, and six special chutes. The entire sorter loop is 375 meters long, and its operating capacity allows for sorting 8,000-9,000 shipments per hour.
Start of adaptation works at the Dispatch and Distribution Hub in Lisi Ogoń
As part of the preparations of the Dispatch and Distribution Hub in Lublin for the installation of a new sorter, on September 30, 2022, Poczta Polska SA and REVBUD SA signed an agreement with the contractor of construction works enabling the subsequent assembly of the machine by BEUMER Group Poland sp. z o. o.
Work will begin in October 2022 and will include interior work on the existing building and the addition of two external facilities. Access roads and maneuvering areas at the new docks will also be modernized.
Completion of adaptation works at the Dispatch and Distribution Hub in Lisi Ogoń
Adaptation work at the Dispatch and Distribution Hub in Lisi Ogon near Bydgoszcz has been completed on schedule. As part of the adaptation work, the existing building was adapted to accommodate the new machine, and the facility also gained 900 square meters of warehouse and office space. Work is currently underway on the installation of an automatic parcel sorting machine (a "Cross-belt" device), manufactured by Beumer.
Machinery at the Expedition and Distribution Hub in Fox Tail
The installation of the sorter for automatic distribution of KEP shipments is progressing according to the established schedule. The sorter's support structure has been installed. The next step will be the assembly of the main sorting line and other components. The sorter is scheduled for commissioning in September 2023.
Launch of the sorter at the Dispatch and Distribution Hub in Lisi Ogoń
The sorter for automatic processing of CEP shipments was launched on schedule. Installation of the sorter was performed by BEUMER Group Poland sp. z o. o. The cross-belt machine has an operating capacity of 8,000-9,000 shipments per hour.
Acquisition of a new logistics facility for Warsaw (WER Ciemne)
To acquire a new logistics facility, Poczta Polska SA and Panattoni have signed a lease agreement for over 50,000 square meters of operational and logistics space. The investment will be built in the Warsaw area and will consist of two facilities, intended to serve as a distribution hub for handling parcel and pallet shipments arriving from other distribution hubs across the country and from within the company's own area of operation, including those sent by bulk customers.
These facilities will include a cross-dock warehouse with an area of over 12,000 m² and a warehouse and operations hall with an area of over 26,000 m². Additionally, support and technical support areas will be located. The investment is currently progressing according to schedule. Panattoni is scheduled to deliver the halls by the end of 2023.
Machinery for the leased logistics facility for Warsaw (WER Ciemne)
On January 19, 2023, Poczta Polska signed an agreement with BEUMER Group Poland sp. z o. o. for the purchase and installation of a sorter for automatic processing of courier, express and parcel shipments.
The sorter purchased by Poczta Polska will be loop-shaped and will utilize cross-belt technology. Featuring six automatic feed lines, six manual feed lines, and over 300 chutes, it will sort parcels down to drop-off points and delivery areas. The device's operational capacity will allow it to sort 15,000 parcels per hour. It will be the largest machine ever operated by Poczta Polska.
Commencement of works related to the machinery upgrade of the leased logistics facility for Warsaw (WER Ciemne)
Work has begun on preparing the sorter installation for automatic parcel sorting. The cross-belt sorter will be designed to process CEP parcels. The machine is being built by BEUMER Group Poland sp. z o. o.
Acceptance of the newly built logistics facility for Warsaw (WER Ciemne)
Poczta Polska (Polish Post) has completed the completion of a new logistics facility located in Ciemne, near Radzymin, near Warsaw. This gives the company its fifteenth forwarding and distribution hub, handling parcel and pallet shipments from other distribution hubs across the country and from within its own service area, including those sent by bulk customers.
Launch of a sorter in a leased logistics facility for Warsaw (WER Ciemne)
According to the adopted schedule, the automated shipment sorter was launched at the newly established Shipping and Distribution Hub in Ciemne near Radzymin. The Cross Belt machine was installed by BEUMER Group Poland Sp. z o. o.
"Supporting households in bearing the costs associated with changing the digital terrestrial television broadcasting standard"
Public task financed from the state budget, part 27, division 750, chapter 75001, section 2830
Funding under a targeted subsidy: the actual value of the funding will be determined based on the number of tasks completed
Total project value: PLN 16,730,323
Implementation period: 21.03.2022 – 31.12.2022
Project description
In 2022, the digital terrestrial television broadcasting standard will change in Poland, requiring some members of the public to adapt their digital terrestrial television receiving equipment to the new standard. The legislature has provided support for households through the possibility of obtaining a benefit for the purchase of a digital receiver, referred to in the Act of February 24, 2022, on supporting households in bearing the costs associated with the change of the digital terrestrial television broadcasting standard (Journal of Laws, item 501) (hereinafter referred to as the "Act"). At the same time, the legislature has deemed it appropriate to allow interested parties to submit applications for benefits for the purchase of a digital receiver not only electronically but also in paper form, which requires the provision of publicly accessible locations where applications can be submitted in person.
The task entitled – “Supporting households in bearing the costs associated with the change of the digital terrestrial television broadcasting standard” is a task resulting from Article 14, paragraph 2, Article 17 and Article 25, paragraphs 4 and 5 of the Act, consisting in accepting applications for a benefit for the purchase of a digital receiver, making payments for a document confirming the granting of the benefit to an entrepreneur selling digital receivers and conducting promotional activities regarding the benefit for the purchase of a digital receiver.